Uganda delays first oil exports to 2027 over pipeline delays

Uganda has postponed its first commercial oil exports until the second quarter of 2027, attributing the delay to global supply chain disruptions linked to the conflict in Iran. This adjustment risks a significant budget shortfall, as the government had budgeted for €315.4 million in oil revenue during the 2026/2027 fiscal year. The East African Crude Oil Pipeline (EACOP), which cost $5.6 billion, is now 90% complete but cannot begin operations without finishing pumping stations 3 and 4, as well as security systems and instrumentation. The 1,443-kilometer pipeline to Tanzania’s port of Tanga also requires heating systems, since Uganda’s waxy crude tends to solidify during transport, necessitating an integrated heating solution to maintain fluidity throughout the route.
Beyond the pipeline, technical challenges persist at the Kingfisher and Tilenga projects. Kingfisher is 90% complete, but its central processing facilities remain under installation and testing. Tilenga, at 78% completion, faces similar setbacks. Once fully operational, Uganda expects daily production of 230,000 barrels, beginning with 25,000 barrels from Kingfisher and eventually scaling to 40,000 barrels, while Tilenga will progressively reach 190,000 barrels. The phased ramp-up reflects the staggered completion of infrastructure across both fields.
The delays have exacerbated Uganda’s economic concerns. S&P Global Ratings revised the country’s credit outlook from positive to stable, citing a projected 6% budget deficit by 2027. To address currency depreciation, the central bank raised its benchmark interest rate to 12%. The government now dedicates nearly 30% of its revenue to paying domestic debt interest. Furthermore, S&P has lowered its growth forecast for 2027 to 5.8%, citing factors such as falling coffee prices, the decline in tourism due to Ebola, and geopolitical instability.
Read Also: US Navy Unveils $9B Nuclear Submarine Plan
Uganda’s oil plans now compete with neighboring energy initiatives. Tanzania is collaborating with ExxonMobil, Shell, and Equinor on a $42 billion liquefied natural gas terminal for offshore reserves, positioning itself as a major LNG exporter. Ethiopia has begun the first phase of its Ogaden LNG project, while Aliko Dangote is advancing a large-scale refinery in Kenya. These regional developments further complicate Uganda’s ability to meet its revenue targets, as competing energy projects divert investment and create market saturation risks.
The government had anticipated annual earnings of $1.5 billion to $2.5 billion from its estimated 1.65 billion recoverable barrels of crude. Without these funds, the budget gap will expand, straining public services and debt repayment obligations. The conflict in Iran has worsened the situation by disrupting shipments of essential components for telecoms, electrical instrumentation, and metering systems—critical inputs for Uganda’s oil infrastructure. Without these parts, the final stages of the pipeline and processing plants cannot proceed, prolonging the delay while also exposing the country’s vulnerability to geopolitical supply chain risks.